Project sheet — QLD-200
Queensland 200 MW site under origination.
Transmission corridor identified. Connection enquiry pathway in preparation. This site is at an earlier stage than SEQ-400 — no site control, no capital partner conversations, no tenant engagement. Disclosed at region-only until structural landowner agreement is executed.
Disclosure standard: This site is in origination. Nothing here is confirmed beyond what is explicitly stated. Items marked [VERIFY] are placeholders for Gary to confirm before external distribution of this sheet.
Current status
Where this site sits in the development sequence.
- Stage
- Site origination — shortlist and grid connection screening complete. Structural landowner engagement not yet commenced.
- Disclosure policy
- Region-only naming until a structural landowner agreement is executed. Site address, landowner identity and counterparty detail released on execution. This is operational posture, not pending paperwork.
- Current work
- Site shortlist narrowed. Transmission corridor identified. Connection enquiry pathway in preparation with the relevant TNSP. [VERIFY: Gary to confirm which corridor/TNSP is in scope]
Power
Transmission corridor and connection pathway.
- Transmission corridor
- Identified. Matches a 200 MW envelope. Connection enquiry pathway in preparation — not yet lodged. [VERIFY: Gary to confirm corridor location and TNSP]
- Capacity envelope
- 200 MW target. Connection screening confirms the corridor can support this load profile subject to formal enquiry and augmentation studies.
- Connection application timeline
- Enquiry lodgement planned once site control terms are agreed with the landowner. Indicative 24–36 months to energisation from application lodge, consistent with current Australian TNSP queue conditions.
- BTM assessment
- Not yet scoped at this stage. Will be assessed in parallel with grid-first pathway once site control is advanced.
Site characteristics
Land, zoning, water and fibre at screening level.
- Region
- Queensland. Specific location withheld. Site is grid-adjacent in the identified transmission corridor.
- Land area
- Sufficient for a 200 MW development envelope. Indicative parcel size not disclosed until landowner engagement is formalised. [VERIFY: Gary to confirm approximate hectare range for disclosure]
- Land tenure
- Landowner engagement not yet commenced at the structural agreement level. Pathway identified and screened. Approach strategy in preparation.
- Zoning
- Preliminary assessment complete. Industrial or compatible use confirmed. No rezoning required anticipated for data centre use. [VERIFY: Gary to confirm zoning designation from screening]
- Water and cooling
- Water access pathway identified. Cooling feasibility assessed at screening level — not confirmed against a specific supply agreement. [VERIFY: Gary to confirm water source identified in screening]
- Fibre
- Carrier route logic assessed at screening level. Fibre proximity confirmed. Route survey not yet commissioned. [VERIFY: Gary to confirm carrier and route distance estimate]
Commercial structure
Origination position and stage-appropriate scope.
- What Continode is offering
- The same origination position as SEQ-400 — site identification, grid connection pathway, land control, water and fibre access, and capital structuring — assembled through the Continode development sequence. This site is at an earlier stage than SEQ-400.
- Tenant and capital status
- No tenants engaged at this site. No capital partner conversations commenced. The site must reach site control and connection application stage before investor materials are prepared.
- Commercial structure
- To be determined once site control is achieved. Wholesale colocation and neocloud structures both in scope depending on tenant and capital mandate at that time.
- EPC delivery
- Alliance partner selection deferred until site control and connection application are advanced.
Development timeline
Stage gates from here.
- Current stage
- Site origination. Shortlist complete. Transmission corridor identified. Landowner engagement not yet commenced.
- Next gate
- Landowner approach and structural agreement. Connection enquiry lodgement with TNSP. Parallel capital and tenant dialogue preparation.
- Site control target
- Subject to landowner engagement timeline. No commitment made at this stage. [VERIFY: Gary to confirm target timeline for landowner approach]
- Energisation
- Not foreseeable at this stage. Dependent on site control, connection application, and capital commitment milestones.