Project sheet — QLD-200
Queensland 200 MW site under origination.
Transmission corridor identified. Connection enquiry pathway in preparation. This site is at an earlier stage than SEQ-400 — no site control, no capital partner conversations, no tenant engagement. Disclosed at region-only until structural landowner agreement is executed.
Disclosure standard: This site is in origination. Nothing here is confirmed beyond what is explicitly stated. Site-specific detail withheld until site control is advanced; full information available to confirmed counterparties under NDA.
Current status
Where this site sits in the development sequence.
- Stage
- Site origination — shortlist and grid connection screening complete. Structural landowner engagement not yet commenced.
- Disclosure policy
- Region-only naming until a structural landowner agreement is executed. Site address, landowner identity and counterparty detail released on execution. This is operational posture, not pending paperwork.
- Current work
- Site shortlist narrowed. Transmission corridor identified. Connection enquiry pathway in preparation with the relevant TNSP. TNSP identity withheld until site control is advanced; confirmed in briefing to parties under NDA.
Power
Transmission corridor and connection pathway.
- Transmission corridor
- Identified. Matches a 200 MW envelope. Connection enquiry pathway in preparation — not yet lodged. Corridor location and TNSP disclosed to parties under NDA at site control stage.
- Capacity envelope
- 200 MW target. Connection screening confirms the corridor can support this load profile subject to formal enquiry and augmentation studies.
- Connection application timeline
- Enquiry lodgement planned once site control terms are agreed with the landowner. Indicative 24–36 months to energisation from application lodge, consistent with current Australian TNSP queue conditions.
- BTM assessment
- Not yet scoped at this stage. Will be assessed in parallel with grid-first pathway once site control is advanced.
Site characteristics
Land, zoning, water and fibre at screening level.
- Region
- Queensland. Specific location withheld. Site is grid-adjacent in the identified transmission corridor.
- Land area
- Sufficient for a 200 MW development envelope. Indicative parcel size not disclosed until landowner engagement is formalised.
- Land tenure
- Landowner engagement not yet commenced at the structural agreement level. Pathway identified and screened. Approach strategy in preparation.
- Zoning
- Preliminary assessment complete. Industrial or compatible use confirmed. No rezoning required anticipated for data centre use. Zoning designation confirmed in site screening materials.
- Water and cooling
- Water access pathway identified. Cooling feasibility assessed at screening level — not confirmed against a specific supply agreement. Water source confirmed in site screening materials; supply agreement to be finalised at site control stage.
- Fibre
- Carrier route logic assessed at screening level. Fibre proximity confirmed. Route survey to be commissioned at site control stage. Carrier and route distance detail available in screening materials.
Commercial structure
Origination position and stage-appropriate scope.
- What Continode is offering
- The same origination position as SEQ-400 — site identification, grid connection pathway, land control, water and fibre access, and capital structuring — assembled through the Continode development sequence. This site is at an earlier stage than SEQ-400.
- Tenant and capital status
- No tenants engaged at this site. No capital partner conversations commenced. The site must reach site control and connection application stage before investor materials are prepared.
- Commercial structure
- To be determined once site control is achieved. Wholesale colocation and neocloud structures both in scope depending on tenant and capital mandate at that time.
- EPC delivery
- Alliance partner selection deferred until site control and connection application are advanced.
Development timeline
Stage gates from here.
- Current stage
- Site origination. Shortlist complete. Transmission corridor identified. Landowner engagement not yet commenced.
- Next gate
- Landowner approach and structural agreement. Connection enquiry lodgement with TNSP. Parallel capital and tenant dialogue preparation.
- Site control target
- Subject to landowner engagement timeline. No commitment made at this stage. Target timeline for landowner approach to be confirmed once the approach strategy is finalised.
- Energisation
- Not foreseeable at this stage. Dependent on site control, connection application, and capital commitment milestones.