Australian hyperscale infrastructure

Hyperscale infrastructure for Australia. Sourced, structured and held as institutional capacity.

Continode originates powered land and structures the capital to hold Australian hyperscale data centre capacity as institutional infrastructure. End to end, from site identification to operating partnership.

400 MWSEQ-400 master planStaged 80 / 200 / 40080 MWStage 1 parcel assembled5states in the pipeline

Three ways to engage

Capital, tenants and land, each with a direct path to the senior team.

01

Capital partners

Ownership vehicle, return profile, AUD currency exposure and FIRB clearance pathway, structured for each site before the capital conversation begins.

02

Hyperscale tenants and neocloud operators

Power redundancy, cooling specification, rack density, Tier classification and commissioning window drive the facility design.

03

Landowners with grid-adjacent land

Sites are screened against power, water, fibre, land tenure, planning and cooling criteria. Confidentiality is the default.

Project pipeline

Two Queensland projects, each at a defined stage.

  1. SEQ-400Stage 180 MWParcel assembled. Grid connection under formal assessment.
  2. SEQ-400Stages 2 and 3400 MWStaged to 200 MW and 400 MW on the same controlled parcel.
  3. QLD-200Second site200 MWOrigination. Transmission corridor identified.

Detail for each project sits on its project sheet. Site addresses and counterparties are released as each structural agreement is executed.

The constraint

Australia has the land, grid assets and capital base to host the next wave of AI infrastructure.

Hyperscale growth is no longer limited by tenant demand. It is constrained by grid connection, land control, cooling, fibre and the capital structure required to convert those inputs into an operating asset.

Continode assembles those inputs before the market prices them as finished assets. We work the grid, the land and the capital stack as one origination problem, not three workstreams.

Headquartered in Australia. Active across Queensland, New South Wales, Victoria, South Australia and Western Australia. International capital is engaged directly through the senior team’s existing network.

Market figures below cite CBA (27 October 2026), the Australian Data Centre Forecast Report Issue 2 (October 2026) and AEMO connection data as at June 2026.

Power market reality

Announced capacity is not deliverable capacity.

Australia has announced far more data centre capacity than the grid can connect on current timelines. Each figure opens to its source.

23GWData centre capacity announced in Australia

CBA, 27 October 2026. 76 per cent of it remains in planning or at an earlier stage.

3.6GWUnder construction or being expanded

CBA, 27 October 2026. A further 2 GW has development approval or is in pre-construction.

1.6GWOperational today, across 163 facilities

Australian Data Centre Forecast Report Issue 2, October 2026, using DC Byte data.

67GWConnection capacity sought from AEMO

225 projects as at June 2026, reported by CBA. Applications overlap, which is why deliverable sites matter.

48monthsLarge load connection, upper range

Transmission and distribution connection process publications and public case timing.

36monthsPrimary HV plant, upper range

Market lead times for transformers and switchgear currently run 24 to 36 months.

Sources: CBA, “Australia’s data centre pipeline growing to $260bn in a decade” (27 October 2026); Data Centres Australia, Australian Data Centre Forecast Report Issue 2 (October 2026); AEMO connection data as reported by CBA; network operator connection process publications.

The four inputs

Every viable hyperscale site starts with power, water, fibre and land.

First workstream

Power

Connection strategy, network engagement, redundancy planning, substation scope and behind-the-meter generation packaging.

Power engagement is treated as the first commercial workstream, not a late technical dependency.
Cooling envelope

Water

Potable and process water review, cooling pathway analysis, permitted use history and operating resilience assessment.

Cooling resilience is assessed with water access, energy intensity and permitting in one view.
Route diversity

Fibre

Carrier route potential, path diversity, MOFN structure, subsea adjacency and terrestrial latency constraints.

Fibre strategy prioritises diversity, carrier optionality and subsea adjacency where relevant.
Tenure first

Land

Brownfield origination, tenure review, easements, planning constraints, expansion area and industrial compatibility.

Land is only considered viable when tenure, easements, planning and expansion logic support hyperscale use.

For landowners

Site criteria for stranded grid capacity.

  • 15+ hectares preferred, with expansion logic.
  • Within 5km of transmission infrastructure where possible.
  • Potable and process water access or clear path to supply.
  • Fibre proximity, carrier route potential and path diversity.
  • Industrial or compatible zoning with easements understood.
  • Clear ownership structure and willingness to explore long term value creation.

Grid headroom

Australian power grid headroom map for large load origination.

ACT: Not active, InactiveNSW1: 50-150 MW, Moderate headroomNT: Not active, Outside NEMQLD1: 400 MW staged, High headroomSA1: 45 MW, ConstrainedTAS1: Under review, ModerateVIC1: 50-150 MW, Moderate-constrainedWA SWIS: 50-150 MW, Outside NEMQLD1400MW stagedNSW150-150MWVIC150-150MWSA145MWWA SWIS50-150MWTAS1Under reviewNTNot active

Data sources: AEMO ISP 2024 to 2026 publications and network operator transmission annual planning reports. Regional ranges are indicative; site capacity is confirmed in connection studies.

Source discipline

Headroom and lead times are indicative regional ranges drawn from AEMO ISP material, network operator transmission annual planning reports and connection process publications, refreshed quarterly.

Site-level capacity is confirmed through formal connection studies with the network operator before any figure is relied on in a transaction.

Connection process

The Australian connection journey, shown as a working sequence.

01Early Engagement2 to 6 weeks

Network context, load range and early site constraints are tested before formal lodgement.

02Connection Enquiry4 to 8 weeks

Initial options are requested with load, timing and technical envelope defined.

03Options Report8 to 16 weeks

Powerlink and distribution options are compared for timing, cost, easements and resilience.

04Connection Application12 to 24 weeks

Detailed technical studies, design basis, system impact and commercial assumptions are assembled.

05Negotiation3 to 9 months

Connection terms, scope allocation, security, milestones and project interfaces are resolved.

06Offer to ConnectMilestone based

Formal offer proceeds into execution documents and delivery governance.

07Construction18 to 36 months

Long lead plant, civil works, substations, fibre and facility works are coordinated.

08EnergisationCommissioning

Testing, handover and operational readiness gates are completed before tenant activation.

Methodology walkthrough

Assess4 to 8 weeks

Work: Review load potential, site constraints, network context, water, fibre, land tenure, cooling envelope and early planning issues.

Stakeholders: Landowner, network operator, planning advisor, water authority, fibre carrier and technical lead.

Outputs: Site viability memo, constraint register, connection pathway shortlist and board level recommendation.

Structure6 to 12 weeks

Work: Shape ownership, leasing, energy, PPA, carbon, planning and capital pathways before cost is locked in.

Stakeholders: Capital partner, legal counsel, network operator, energy advisor and tenant side technical representative.

Outputs: Commercial structure, risk allocation paper, consent path and investor ready transaction outline.

Originate8 to 20 weeks

Work: Secure site control, progress connection engagement, coordinate delivery partners, establish tenant dialogue and prepare diligence room.

Stakeholders: Landowner, construction partner, equipment suppliers, fibre carriers, government and prospective tenants.

Outputs: Controlled site, diligence pack, grid status paper, engagement record and phase one delivery budget.

DeliverProject specific

Work: Move from controlled site to powered shell, base build or operated capacity depending on tenant preference and capital mandate.

Stakeholders: Tenant, EPC contractor, operator, network operator, lender, insurer, regulator and owner representative.

Outputs: Delivery governance, reporting cadence, procurement tracker, risk register and operational readiness plan.

AI compute density

Rack density is the physical design problem behind AI infrastructure.

100kW

H100 dense AI

Full liquid plumbing

Sources: NVIDIA published system guidance, Uptime Institute density classifications and ASHRAE TC9.9.

Capability calculator

Indicative scope logic for tenants and capital partners.

Indicative output

Powered shell plus AI ready base build

Cost band
AUD $0.88B to $1.44B indicative build band
Delivery
36 to 54 months
Constraint
Connection pathway and equipment reservation should be treated as the first workstream.
Enquire about this scope

Standards and frameworks

The frameworks every Continode site is designed against.

National Electricity RulesAEMO connection proceduresUptime Institute Tier III and Tier IV classificationsASHRAE thermal guidelinesISO 27001 information securityISO 22301 business continuityVerra Verified Carbon StandardICVCM Core Carbon PrinciplesCSRD aligned reportingTCFD aligned disclosureQueensland planning frameworksFederal Critical Infrastructure Security ActFIRB clearance pathways

Insights

Field notes on power, capital and site selection in Australian hyperscale.

Ecosystem

The categories Continode coordinates to turn powered land into operating capacity.

Utility and Network

Engaging with Australian transmission network operators, distribution networks, fibre carriers and energy market bodies serving Queensland, NSW, Victoria, South Australia and Western Australia.

Equipment and Construction

In dialogue with global HV equipment manufacturers, substation specialists, cooling suppliers and construction groups with complex industrial delivery experience.

Capital

Structured for conversations with super funds, infrastructure funds, sovereign investors, strategic capital partners and long duration family capital.

Carbon and Compliance

Aligned with affiliated CarbonBridge capability, renewable procurement, carbon attestation and reporting frameworks.

Standards Bodies

Mapped to Uptime Institute, ISO, ASHRAE, Australian critical infrastructure requirements and relevant planning regimes.

Enquire

Reach our team directly.

Every Continode engagement is led by the senior management team. Tell us who you are, what you need and when. For the fastest response, email info@continode.com.

For hyperscale tenants

For capital partners

For government, landowners and suppliers