continodeEnquire

Australian hyperscale infrastructure

Hyperscale infrastructure for Australia. Sourced, structured and held as institutional capacity.

Continode originates powered land, structures the capital and holds Australian hyperscale data centre capacity as institutional infrastructure. End to end, from site identification to operating partnership.

525 MWin progressAustralia-wide5states in developmentGLOBALcapital corridor live

The constraint

Australia has the land, grid assets and capital base to host the next wave of AI infrastructure.

Hyperscale growth is no longer limited by tenant demand. It is constrained by grid connection, land control, cooling, fibre and the capital structure required to convert those inputs into an operating asset.

Continode assembles those inputs before the market prices them as finished assets. We work the grid, the land and the capital stack as one origination problem, not three workstreams.

Headquartered in Australia. Active across Queensland, New South Wales, Victoria, South Australia and Western Australia. International capital is engaged directly through the senior team’s existing network.

Source framework: AEMO publications, network operator connection processes, CBRE, JLL, Cushman & Wakefield, Synergy Research Group and public market material. Figures are cited as the underlying source records are released.

Power market reality

Numbers that explain why deliverable capacity matters.

Indicative model for launch review. Each figure reveals source methodology, with quarterly refresh after the research pack is verified.

0MWNEM demand snapshot

AEMO public market data. Phase one uses representative launch values pending live feed integration.

0.0GWAnnounced hyperscale capacity

Public operator filings, market reports and infrastructure news sources under verification.

0.0GWEnergised hyperscale capacity

Public operator disclosures and facility commissioning records under verification.

0.0GWIndicative large load headroom

AEMO ISP and network operator planning reports. First verified release Q3 2026.

0monthsLarge load connection lead time

Transmission and distribution connection process publications and public case timing.

0monthsHV plant lead time

Supplier lead time notes and network procurement observations under verification.

Sources: AEMO ISP, network operator transmission annual planning reports, public operator filings, ASX disclosures, DCD, Bisnow Australia and company announcements. First full source pack scheduled for Q3 2026.

The four inputs

Every viable hyperscale site starts with power, water, fibre and land.

Confirmed pathway

Power

Connection strategy, network engagement, redundancy planning, substation scope and behind-the-meter generation packaging.

Power engagement is treated as the first commercial workstream, not a late technical dependency.
Established access

Water

Potable and process water review, cooling pathway analysis, permitted use history and operating resilience assessment.

Cooling resilience is assessed with water access, energy intensity and permitting in one view.
Route logic mapped

Fibre

Carrier route potential, path diversity, MOFN structure, subsea adjacency and terrestrial latency constraints.

Fibre strategy prioritises diversity, carrier optionality and subsea adjacency where relevant.
Controlled parcel

Land

Brownfield origination, tenure review, easements, planning constraints, expansion area and industrial compatibility.

Land is only considered viable when tenure, easements, planning and expansion logic support hyperscale use.

For landowners

Site criteria for stranded grid capacity.

Grid headroom

Australian power grid headroom map for large load origination.

ACT - Not active - InactiveNSW1 - 50-150 MW - Moderate headroomNT - Not active - Outside NEMQLD1 - 400 MW staged - High headroomSA1 - 45 MW - ConstrainedTAS1 - Under review - ModerateVIC1 - 50-150 MW - Moderate-constrainedWA SWIS - 50-150 MW - Outside NEMQLD1400MW stagedNSW150-150MWVIC150-150MWSA145MWWA SWIS50-150MWTAS1Under reviewNTNot active

Data sources: AEMO ISP 2024 to 2026 publications, network operator transmission annual planning reports. Figures indicative. Data being verified for first release Q3 2026.

Source discipline

Indicative headroom, lead times and constraints are staged for quarterly refresh from AEMO ISP material, network operator transmission annual planning reports, connection process publications and public regulatory sources.

No capacity figure is presented as final until source notes and date stamps are published.

Connection process

The Australian connection journey, shown as a working sequence.

01Early Engagement

Typical duration: 2 to 6 weeks

Network context, load range and early site constraints are tested before formal lodgement.

02Connection Enquiry

Typical duration: 4 to 8 weeks

Initial options are requested with load, timing and technical envelope defined.

03Options Report

Typical duration: 8 to 16 weeks

Powerlink and distribution options are compared for timing, cost, easements and resilience.

04Connection Application

Typical duration: 12 to 24 weeks

Detailed technical studies, design basis, system impact and commercial assumptions are assembled.

05Negotiation

Typical duration: 3 to 9 months

Connection terms, scope allocation, security, milestones and project interfaces are resolved.

06Offer to Connect

Typical duration: Milestone based

Formal offer proceeds into execution documents and delivery governance.

07Construction

Typical duration: 18 to 36 months

Long lead plant, civil works, substations, fibre and facility works are coordinated.

08Energisation

Typical duration: Commissioning

Testing, handover and operational readiness gates are completed before tenant activation.

Methodology walkthrough

Assess4 to 8 weeks

Work: Review load potential, site constraints, network context, water, fibre, land tenure, cooling envelope and early planning issues.

Stakeholders: Landowner, network operator, planning advisor, water authority, fibre carrier and technical lead.

Outputs: Site viability memo, constraint register, connection pathway shortlist and board level recommendation.

Structure6 to 12 weeks

Work: Shape ownership, leasing, energy, PPA, carbon, planning and capital pathways before cost is locked in.

Stakeholders: Capital partner, legal counsel, network operator, energy advisor and tenant side technical representative.

Outputs: Commercial structure, risk allocation paper, consent path and investor ready transaction outline.

Originate8 to 20 weeks

Work: Secure site control, progress connection engagement, coordinate delivery partners, establish tenant dialogue and prepare diligence room.

Stakeholders: Landowner, construction partner, equipment suppliers, fibre carriers, government and prospective tenants.

Outputs: Controlled site, diligence pack, grid status paper, engagement record and phase one delivery budget.

DeliverProject specific

Work: Move from controlled site to powered shell, base build or operated capacity depending on tenant preference and capital mandate.

Stakeholders: Tenant, EPC contractor, operator, network operator, lender, insurer, regulator and owner representative.

Outputs: Delivery governance, reporting cadence, procurement tracker, risk register and operational readiness plan.

AI compute density

Rack density is the physical design problem behind AI infrastructure.

100kW

H100 dense AI

Full liquid plumbing

Source attribution before launch: NVIDIA published system guidance, Uptime Institute density classifications and ASHRAE TC9.9.

Capability calculator

Indicative scope logic for tenants and capital partners.

Indicative output

Powered shell plus AI ready base build

Cost band
AUD $0.88B to $1.44B indicative build band
Delivery
30 to 42 months
Constraint
Connection pathway and equipment reservation should be treated as the first workstream.
Discuss further

Capacity tracker

Continode pipeline: announced and in-progress capacity.

Continode740MW announced525MW in progressINDICATIVE · Q3 2026 VERIFICATION PENDING

Indicative pipeline figures. SEQ-400 Stage 1 (80 MW) is assembled. QLD-200 and remaining pipeline are in origination. First full data release Q3 2026.

Standards and frameworks

Mapped to the regimes that matter for power, security, continuity, carbon and ownership.

National Electricity RulesAEMO connection proceduresUptime Institute Tier III and Tier IV classificationsASHRAE thermal guidelinesISO 27001 information securityISO 22301 business continuityVerra Verified Carbon StandardICVCM Core Carbon PrinciplesCSRD aligned reportingTCFD aligned disclosureQueensland planning frameworksFederal Critical Infrastructure Security ActFIRB clearance pathways

Insights

Market work staged with dates, source notes and clear versioning.

Data tracker modules

Announced capacity versus delivered capacity, connection lead times by network operator, HV plant lead time notes and public regulatory updates.

Ecosystem

The categories Continode coordinates to turn powered land into operating capacity.

Utility and Network

Engaging with Australian transmission network operators, distribution networks, fibre carriers and energy market bodies serving Queensland, NSW, Victoria, South Australia and Western Australia.

Equipment and Construction

In dialogue with global HV equipment manufacturers, substation specialists, cooling suppliers and construction groups with complex industrial delivery experience.

Capital

Structured for conversations with super funds, infrastructure funds, sovereign investors, strategic capital partners and long duration family capital.

Carbon and Compliance

Aligned with affiliated CarbonBridge capability, renewable procurement, carbon attestation and reporting frameworks.

Standards Bodies

Mapped to Uptime Institute, ISO, ASHRAE, Australian critical infrastructure requirements and relevant planning regimes.

Utility and NetworkEquipment and ConstructionCapitalCarbon and ComplianceStandards Bodies

Enquire

Reach our team directly.

Every Continode engagement is led by the senior management team. Tell us who you are, what you need and when. Email is faster than the forms below - info@continode.com reaches our consultant team.

For hyperscale tenants
For capital partners
For government, landowners and suppliers